Grid tie inverter: string design and sizing rules

A grid tie inverter is the cheapest way to turn roof area into kilowatt-hours — as long as the string voltage survives the coldest morning on that roof. Here are the four numbers that decide it.

PV array 200–500 V DC Battery 48 V nominal House 120 / 230 V AC Grid or genset MPPT DC → AC Transfer relay 1 2 3 4 5

Anatomy

Five connections decide which model fits. Ask for the datasheet to confirm each one on the exact rating you are buying.

  1. 1PV DC inputString voltage window and max input current per tracker.
  2. 2MPPT trackerOne tracker per roof orientation; two trackers help a partly shaded array.
  3. 3Battery portNominal voltage and chemistry must match the bank you already own.
  4. 4AC outputContinuous and surge rating, and whether the backup panel is separate.
  5. 5Grid or genset inputGrid-code approval for your country, plus generator start support.

What a grid tie inverter does

A grid tie inverter pushes everything the array produces straight into the house and then into the grid. There is no battery in the usual design, no backup output, and no need to decide what happens at night: the grid supplies the house after sunset. Because there is no battery, the cost per installed watt is the lowest of any inverter family, which is why most residential solar in the US, Europe and Australia uses one.

String design in one page

A string inverter takes DC from panels wired in series. Four numbers on the datasheet decide whether a particular array works:

  • Maximum DC input — the array's STC wattage must sit under it, with oversizing commonly 1.1–1.3× the AC rating.
  • MPPT window — the string's voltage at high temperature (worst case) must stay above the bottom of the window, and at record low temperature must stay below the maximum system voltage, usually 500 V or 1000 V.
  • Start voltage — below this, the inverter does not wake up even if there is light.
  • Strings per MPPT — one MPPT serves panels of the same orientation. A roof with east and west faces needs either two MPPTs or two inverters.

Most designs fail the temperature check rather than the power check. A string of ten 40 V panels shows 400 V on a bench, but at −10 °C the same string sits near 450 V, and on a hot roof it sags toward 320 V.

Where string inverters lose

Shade is the weak point. One shaded panel drags the whole string down unless optimisers or module-level electronics are added. Mixed orientations on a complex roof, small arrays split across two planes, and long cable runs between roof and inverter room can all make microinverters or optimisers cheaper than the string design that avoids them.

Anti-islanding and grid codes

A grid tie inverter must stop exporting when the grid is down; that is anti-islanding protection, required for line-worker safety, and it is not something to defeat. Beyond that, the unit must carry the grid code certificate of the country where it is installed — IEEE 1547 and UL 1741 in the US, G98/G99 in the UK, VDE-AR-N 4105 in Germany, AS/NZS 4777.2 in Australia. A cheap unit without the local certificate may work electrically and still be refused at inspection.

Sizing example

A house with 14 × 400 W panels (5.6 kW STC) on two roof faces wants a 5 kW string inverter with two MPPTs. Each face gets its own string, so the morning and afternoon peaks do not have to share a tracker. Expected output is limited by the smaller face at the ends of the day, which is exactly what two trackers fix.

When to choose something else

Choose a hybrid if a battery is likely within a few years, because the grid tie unit has no battery port. Choose microinverters if the roof is shaded or split into many planes. Choose an off grid inverter if there is no utility at all. The grid tie box is the right answer only when exporting is the whole job.

FAQ

Common questions

How much array can I connect to a grid tie inverter?

Commonly 1.1–1.3 times the inverter's AC rating on the DC side. The limit comes from clipping losses versus the gain of more panels: above roughly 1.4×, the energy lost at midday outweighs the extra array.

How do I check string voltage at low temperature?

Add up the panel open-circuit voltages and multiply by the coldest expected temperature coefficient, then check the result against the maximum system voltage on the datasheet. Also check the string voltage at 60–70 °C cell temperature against the bottom of the MPPT window.

Can I install a grid tie inverter without utility approval?

Electrically yes, legally usually no. The unit must carry the grid code certificate for the country and be installed by an approved person; otherwise the utility can refuse the connection and the warranty may not apply.

Will a grid tie inverter run during a power cut?

No. Anti-islanding protection shuts the unit down when the grid fails, which is required for line-worker safety. A grid tie inverter cannot provide backup; a hybrid with a backup output or an off grid inverter is the alternative.